The Upper Ganga Canal Expressway is back on track! After years of delays, the UPEIDA (Uttar Pradesh Expressways Industrial Development Authority) restarted construction in 2025, promising faster connectivity between Uttar Pradesh and Uttarakhand.
In this blog, we’ll cover: Latest project updates
Route map & key details
Why it was delayed for 11 years
Major benefits for commuters & businesses
Impact on real estate & tourism
Let’s dive in!
1. Upper Ganga Canal Expressway: Key Facts (2025)
Particulars | Details |
Project Length | ~150 km |
Project Cost | ₹8,700 Crores |
Lanes | 8-Lane Expressway |
Start Point | Sanauta Bridge, Bulandshahr |
End Point | Purkazi, Muzaffarnagar |
Expected Completion | November 2025 |
2. Upper Ganga Canal Expressway Route & Map
The expressway will parallel the Upper Ganga Canal, improving connectivity between Noida, Greater Noida, and Uttarakhand.
Major Cities Connected:
Greater Noida
Gautam Buddha Nagar
Bulandshahr
Meerut
Ghaziabad
Muzaffarnagar
Saharanpur
Key Features:
147.8 km (8-lane main expressway)
68.5 km (6-lane link expressway)
97.3 km (2-lane service road)
Land parcels for development at 6 locations
Hydroelectric power upgrades at 7 canal falls
Link Expressways Included:
23.5 km – Connects to Meerut Airport & DFC Terminal
16.5 km – Purkazi to Deoband
3.5 km – NH-24 (Masuri) to Dasna Fall
Two future links (25 km each)
3. Why Was the Upper Ganga Canal Expressway Delayed?
The project was first launched in 2013 but faced multiple hurdles: Land acquisition issues
Funding delays
Administrative challenges
Originally called the Hindon Expressway, the route was changed in 2009 due to land disputes, shortening it by 80 km. After 11 years of delays, construction has finally resumed, with completion expected by November 2025.
4. Top Benefits of the Upper Ganga Canal Expressway
1. Faster Travel Between UP & Uttarakhand
Reduces travel time between Noida, Meerut, Muzaffarnagar & Dehradun
Smoother commute for tourists & daily travelers
2. Boosts Economic Growth
Improves trade & industrial development
Attracts investments in nearby areas
3. Enhances Freight Movement
Reduces logistics costs for businesses
Better connectivity to Dedicated Freight Corridor (DFC)
4. Promotes Tourism in Uttarakhand
Easier access to hill stations & pilgrimage sites
Reduces congestion on existing routes
5. Environmental & Infrastructure Benefits
7 hydroelectric power stations to be upgraded
8-lane modern expressway with service roads
Impact on Real Estate Near Upper Ganga Canal Expressway
The new expressway is expected to boost property demand in: Noida & Greater Noida – Better connectivity to Uttarakhand
Meerut & Muzaffarnagar – Industrial & commercial growth
Ghaziabad & Bulandshahr – Rising residential & commercial projects
Investors are eyeing land parcels along the route, making it a hotspot for future development.
5. Conclusion: A Game-Changer for North India
The Upper Ganga Canal Expressway is set to transform travel and trade between UP & Uttarakhand. With 8 lanes, improved infrastructure, and better connectivity, it will: Reduce traffic congestion
Cut travel time
Boost real estate & tourism
Enhance economic growth
Stay tuned for more updates as the November 2025 deadline approaches!
Also Read: Purvanchal Expressway : Route Map, Connectivity with Other Expressways