1. New Expansion of Hyd Metro Project:

The state government approved Hyderabad’s metro rail network expansion with an INR 69,100 crore investment for basic infrastructure development. In the third phase, the metro will be extended by 278 kilometers, connecting new areas with fifteen new corridors.

The authorities will create four new corridors in the southwest, extending from Pharma City to Kandukur via Shamsabad Airport.

Hyderabad's new metro line
Hyderabad’s new metro line

2. The decision for Metro Rail Network

Hyderabad’s authorities expect this expansion to address transportation, and traffic, and reflect the city’s continuous growth, rapid development, and increased population. The expansion plan will cover the Vishwanathapuram area and other densely populated regions with efficient metro connectivity.

The metro is currently covering about 70 kilometers, and the new expansion will take it up to 278 kilometers, connecting areas from Rayadurgam to Shamsabad Airport.

3. New Metro Lines

The Hyderabad metro extension will include various metro lines, double-decker metro rail systems, and elevated corridors. It will connect areas from Miyapur to Lakdikapul, Vijayawada to Hayatnagar, Uppal to Yadadri Bhuvanagiri district, and extend the metro to Kothur-Shadnagar. Additionally, the plan includes a new metro corridor from ECIL to LB Nagar, spanning 5.5 kilometers.

4. Phases of the Metro Expansion

The second phase will extend the metro by 31 kilometers from Rayadurgam to Shamsabad Airport. In the third phase, the metro will expand by 26 kilometers from BHEL-Miyapur-Gachibowli-Lakdikapul, and five kilometers from Nagole to LB Nagar, with an estimated INR 9,100 crore investment. The state government has already sent a proposal to the central government for financial support to implement this project.

3rd Phase-A:

Metro Expansion LineAlignmentLength (Km)No. of Include Stations Budget
BHEL-Patancheru-IsnapurElevated13km8 StationsRs.3250/- Crores
LB Nagar-Hayath Nagar-Pedda AmberpetElevated13km8 StationsRs.3250/- Crores
Shanshabad-Kothur-ShadnagarElevated28km6 StationsRs.6800/- Crores
Uppal-Ghatkesar-BB NagarElevated25km10 StationsRs.6900/- Crores
Shamshabad Airport-Tukkuguda-KandukurElevated26km8 StationsRs.6600/- Crores
Tarnaka-ECILElevated8km5 StationsRs.2300/- Crores
JBS-TumkuntaDouble Elevated13km13 StationsRs.5690/- Crores
Paradise-KandlakoyaDouble Elevated10km10 StationsRs.4400/- Crores

3rd Phase-B:

Metro Expansion LineAlignmentLength (Km)Budget
Shamshabad-Tukkuguda-Bonguluru-Pedda AmberpetElevated/UnderGround40kmRs.5,600/- Crores
Pedda Amberpet-Ghatkeasar-Shamirpet-MedchalElevated/UnderGround45kmRs.6,700/- Crores
Medchal-Dundigal-PatancheruElevated/UnderGround29kmRs.4,785/- Crores
Patancheru-Kokapet-NarsingiElevated/UnderGround22kmRs.3,675/- Crores

Hyderabad metro extension ensures improved connectivity and transportation in response to rapid urbanization and growth.

Also, Read Our Latest Blog Posts:

Frequently Asked Questions

1Q: How much will the Hyderabad New Metro Line expansion cover?

Ans: The expansion will cover an additional 278 kilometers of metro corridors, connecting new areas and neighborhoods.

2Q: How much Budget will be Spent on Hyderabad’s New Metro Line expansion?

Ans: Rs.69,100/- crore Budget will be Spent on Hyderabad’s New Metro Line expansion.